BRIDGES COMPONENTS
The project also consists of the construction of road and railway
bridges to replace the Causeway. The removal ofthe Causeway will
be followed by the dredging of a navigation channel to allow
passage of vessels.
RELOCATION OF WATER MAINS
Existing Water Mains, which are routed along Jalan Bukit Chagar,
have been relocated to facilitate the construction of the CIQ
Complex, while the Water Mains along Jalan Jim Quee have been
relocated to facilitate the construction of JB Sentral and internal
roads. In addition to the diversion of the major Water Mains, other
SAJ Water Mains serving the surrounding areas have also been
diverted and upgraded to serve the additional needs of the
Integrated CIQ Complex and ancillary buildings.
The Water Mains running along the Causeway will be replaced
with submarine pipes, and where necessary, the pipes will
be protected by armour protection units. Cathodic protection will
be applied to the submarine pipes to prevent corrosion.
http://www.gerbangperdana.com.my/
then cliick ''Learn more about the Gerbang Selatan Bersepadu
(GSB)
Project located at Bukit Chagar, JB''
then ''components of gsb''
Identification of Water Mains (landside) relocation


above:the overall plan.Left bottom corner is current Johor
CIQ
Read also ABOUT THE PROJECT.
2.MY already made decisions for Sg!