My precinct currently undergoes MUP, it has been slightly more
than 2years. However it seems the MUP might take a year more to
complete.
I had sent several emails to the project manager from Surbana.
Other than the first email which I cc to my MP, the other 2 emails,
he simply ignore.
My patience is running out, the 2 lifts took 2 years to retrofit
(and at last).
To update all on the progress, after 2 years:
a. 3 lifts still undergoing upgrading. The 3 lifts started
upgrading only in Aug 04.
b. lift lobbies for the other 3 lifts still not complete. Despite
the 3 lifts commissioned in Jul 04.
c. lighting not complete, despite started to retrofit lighting in
Oct 04.
d. roof top railing not complete, despite start to retrofit in Oct
04.
e. new letter boxes, nowhere in sight.
f. repainting not even started, despite stated to start in Nov
04.
g. rewiring not complete, even though it has been ongoing since
Sep04.
h. amphitheatre started aggressively for 3 months, and now seems to
stop totally.
i. all projects do not seem to have completed.
What can a resident do to request HDB, Surbana to expedite the MUP?
What' more frustrating the project manager refuse to reply to my
email, refuse to state when is the expected completed date for my
precinct.
And my precinct is Holland Park View.
Do you have similar experiences?