Surprisingly, the same subject
is headlined in the Malaysian NEW STRAITS TIMES in a more balanced
and "truthful" manner, as seen from the following extract
:
----------------------------------------------
New Straits Times » Frontpage
Reclamation
to be monitored
Deborah Loh
HAMBURG, Oct 9: SHORT of ordering
a total suspension of Singapores reclamation
works, the International Tribunal for the Law of
the Sea (ITLOS) yesterday directed the republic
not to conduct its reclamation in ways
that would cause irreparable prejudice to Malaysias rights or
serious harm to the marine environment.
The tribunal also ordered Singapore to subject its reclamation
works to a group of independent experts who would study its effects
and propose appropriate measures to deal with any adverse
impact.
The order was read by tribunal president L. Dolliver M.
Nelson.
Also on the bench were all 21 permanent judges of the tribunal, and
the two ad hoc judges appointed by Malaysia and Singapore.
The tribunal ordered both countries to co-operate in promptly
setting up the group of experts and jointly agree on the terms of
reference of the study, which should be completed within a
year.
The study by the experts was a Malaysian proposal.

It also ordered the study to prepare as soon as possible an interim
report on the infilling works in Area D at Pulau Tekong
(reclamation here has not started).
Malaysia and Singapore are also to have regular exchanges of
information and assessment of risks and effects of the
reclamation.
The order, however, was silent
on the boundary issue of reclamation works affecting the waters at
Point 20 south of Tuas.
Significantly, the ITLOS order noted that Singapore had committed
itself to "carefully study Malaysia's evidence" if Malaysia could
"point to a specific and unlawful adverse effect that would be
avoided by suspending some part of the present works".
Singapore had also said that it would "seriously re-examine its
works and consider taking such steps as are necessary and proper,
including a suspension, to deal with the adverse effect in
question".
Singapore had also informed the tribunal that it would not
take "irreversible action" to construct the stone revetment around
Area D at Pulau Tekong, pending the completion of the joint
study.
The order noted that these commitments by Singapore were
placed on the tribunal's record. Singapore's request that Malaysia bear its costs
incurred in the proceedings was dismissed.
Additionally, the tribunal wants Malaysia and Singapore to submit
to it the first report on compliance with the order by Jan 9.
Present on Malaysia's side were co-agent Ambassador to Germany
Datuk Kamal Ismaun and Attorney-General Tan Sri Abdul Gani Patail.
Singapore was represented by its agent Prof Tommy Koh, its
ambassador-atlarge, and co-agent A. Selvarajah, Singapore's
Ambassador to Germany.
The ITLOS order is equivalent to a judicial order and is,
therefore, legally binding on both parties. Malaysia
decided to apply to ITLOS for interim provisional measures (or an
injunction) on the reclamation works, after Singapore turned down
repeated requests to negotiate the matter. Singapore also did not
respond to Malaysia's requests for an environmental impact
assessment of its works.
The reclamation dispute still has to be settled by a
separate arbitral tribunal.
Malaysia instituted arbitral proceedings under the United Nations
Convention on the Law of the Sea, and on Sept 5, submitted a
request to the ITLOS for the provisional measures.
The hearing of the case was held for three days from Sept 25.
Malaysia had been represented by its agent Foreign Ministry
secretary-general Tan Sri Fuzi Abdul Razak, Gani and international
law experts Sir Elihu Lauterpacht, James Crawford, both professors
of Cambridge University, and Prof Nico Schrijver, a professor of
international law.
Malaysia had argued that a stop to the reclamation works pending
final arbitration was crucial given the irreparable damage to the
marine environment at Pulau Tekong.
Studies were presented to show that continued reclamation would
narrow the distance between the Johor coast and the island, causing
an increase in current velocity, resulting in greater coastal
erosion, siltation and higher salinity in Johor's estuaries. These
effects would destroy coastal habitats.
The shipping lane between Pulau Tekong and the Pularek naval
training base would also be narrowed, causing difficulties in ship
manoeuvrability.
Malaysia said the stoppage of works at Tuas was also
warranted because the affected area in the southern waters of Tuas
(at Point 20) lay within territorial waters claimed by Malaysia
since 1979.
Additionally, Singapore's actions had breached international
obligations owed to Malaysia as a neighbour, which is the duty to
co-operate bilaterally especially since the straits were a
semi-enclosed sea common to both countries.
Singapore had been represented by Koh and Attorney-General Chan Sek
Keong.
Singapore did not accept Malaysia's technical studies as proof of
environmental damage. It blamed marine pollution in the straits on
Malaysia's own development projects. It also argued that the claim
of urgency was not credible as Malaysia knew of the reclamation but
delayed action until works reached an advanced stage.
On the disputed Point 20 south of Tuas, Singapore said the
waters there were within its boundary under a 1995 agreement
ratified by both countries.
If completed, the reclamation would add a total of 3,306ha to Pulau
Tekong, double its original size, while Tuas would be extended
seven kilometres, covering 1,908ha.
http://www.nst.com.my/Current_News/NST/Thursday/Frontpage/20031009081625/Article/