Hi mr busanalyser, found the parliamentary reply. Just some
sayings with future plans to be revealed later. This means still
have to wait for quite a long time. There is no finalized plans
yet. If need to build condo on top of mall and interchange, yr 2020
may not be enough. At least yr 2022. When Punggol central initial
plan was announced in yr 2009, it took until yr 2016 for waterway
point to be up. Moreover the Watertown condo on top is still not
yet ready. Initial plans for condo to be up is end yr
2017.
Buangkok integrated development first surfaced into the news in
yr 2013. Now is already yr 2016 with the same sort of news released
again. This goes to show nothing concrete is happening yet for the
past 3 years. News release still the same old thing stating future
plans to be revealed at a later stage. Cheers. Thanks.
They might speed up Buangkok ITH in case the Sengkang
interchange expansion runs into issues. They may close down the
temp expansion once Buangkok ITH is up.
Otherwise right now there is not really need for Buangkok
interchange given that there will be Bidadari, HG extension,
Sengkang extension and Punggol extension. In that case, Buangkok
ITH can wait for few more years.