I don't think there is a need for that many additional duties
though, If it is extended I'll keep quiet but one big loop means
many temporary add? I don't understand.
The press release clearly states run time will be increased by 4
to 8 min with the additional routing. If you do not wish to
increase fleet size with this change, then bear with longer
headways by 2-5min. And QoS will fail for some
routes just by this change.
Increasing 1 bus will help to maintain the headways to be the
same as before, as well as maintaining QoS.