I don't think it will be this month, more likely next month or
even May 2007.
Why? Take a look at the exit from the new bus interchange. It is
supposed to let the buses turn left into AMK Ave 8 to the bus stop
outside Jubilee, and turn right, into AMK Ave 8, and continue
either to AMK Ave 8 (Svc 22, 24, 135), or turn left into Ave 3
outside the MRT station (Service 25), turn right into AMK Ave 3,
outside blk 322 or blk 324 (Service 166, 169, 133, 130, 138,
etc).
But the centre median of AMK Ave 8 has not been modfied to allow
that turning movement, and the traffic lights are not installed
yet. PowerGrid will take at least 2 weeks to laid the supply in and
another 2 weeks to commission the supply. That's provided LTA RM
side or the Term Contractor submits the application now. I'm not
even sure whether this modification will be donw under LTA's RM
department or will be under the main contractor of the new AMK
Hub.