Nicoll Highway reopens to traffic after
reconstruction
SINGAPORE : Nicoll Highway has reopened more than seven months
after the April 20 construction site cave-in which killed four
people.
Reconstruction started in August, and after three months and S$3
million of repairs, the 48-year-old Nicoll Highway is once more
ready to take on traffic.
There are no traces of the April 20 cave-in.
The accident site has been stabilised and strengthened by 56 piles
going as deep as 50 metres.
Large holes were first drilled into the ground, and then filled
with cement.
The Land Transport Authority says each of the piles can take a load
of 1050 tonnes -- that is the weight of more than 1,000 cars.
The road was then rebuilt over the piles and re-surfaced.
Transport Minister Yeo Cheow Tong road-tested the highway with a
40-vehicle convoy.
While glad that the road was rebuilt in record time, the minister
says a decision on how to proceed with work on the Circle Line MRT
at this site will be made in the coming weeks.
Mr Yeo said, "One option is of course to rebuild over the collapse
area, and excavate where the old line was. The other option is to
go to a different alignment; that means you sacrifice what has been
done and then you do a completely new excavation along the new
alignment.
"Whichever way we take it, it is likely that the Circle Line for
Phase 1 would be delayed by probably up to two years."
Bus services plying Nicoll Highway will resume on Monday.
Electronic Road Pricing (ERP) gantries at Kallang Road and Nicoll
Highway will also be activated on the same day.
With the reopening, ERP rates for the ECP gantry at Fort Road will
be reduced accordingly.
While the reopening of the Nicoll Highway closes a chapter of the
cave-in, the hearing into the cause of the collapse
continues.
From December 7, the Committee of Inquiry will be taking a break,
and will reconvene in January next year. More key witnesses are
expected to testify.