Paya Lebar CCL station box is completed. Now the construction of
entrance/exit box and linkway between CCL and EWL currently is in
progress. Once the linkway between EWL and CCL is completed, the
road will eventually be restored back to their original position.
But they are pretty faster than Mountbatten CCL station on Stage
2.
Mountbatten CCL station construction seemed to be progressing at
quite slow pace. The top roof covering up is about 95% done.
And MacPherson MRT station box is completed. The construction of
entrance/exit box will be completed, following by fittings in two
or more months' times.
Bishan, Bartley, Lor Chuan and Serangoon CCL station follow the
similar suit at MacPherson CCL station in terms of construction
progress pace, meaning that their station box is already completed
and their entrance/exit box will be completed being building and
fitting in few months' times.
For Nicoll Highway CCL station, the construction seemed to be
progressing very slow as I think the constructor is still building
the station box. I really need to check out the progress there one
day.