Unfortunately, I think Manager 433 is right. I asked the guy in
charge of rolling stock on Fri when the C651 will kena refurbish,
but he said "maybe in the next 5 yrs, depending on management".
From their words, I guess they have NO plans for refurbishment for
now?
Or maybe they don't want to say out too much until it's
confirmed? OK, insiders pls help me check out on this.
By the way, the guy at the 'machine shop' says C151 MLU is
hopefully done by end of Sept 08 at the rate of one train per 7-10
days. "The Koreans are working hard..."
I can see that they're working damn hard. :D
After all they're lagging behind, due to the intital rate of 1
train/month when the project first started.
Now it is around 2 trains/month, still below the minima of 4 per
month required.