Tot I do a review of the F-35 current schedule
for production JSF variants. LLF = Long lead funding,
delivery (del) expected 3 years after LLF.
Lot 1 (2): 2 -A (USAF) (LLF: FY06/07, del ~FY 09/10).
Lot 2 (12): 6 -A (USAF), 6 -B (USMC) (LLF: FY07/08, del ~FY
10/11).
Lot 3 (23): 12 -A (10 USAF, 2 Dutch), 11 -B (8 USMC, 3 UK) (LLF:
FY08/09, del ~FY 11/12).
Lot 4 (28): 13 -A (12 USAF, 1 Dutch), 14 -B (USMC), 1 -C (USN)
(LLF: FY09/10, del ~FY 12/13).
Lot 1/2 likely used for operational testing.
Numbers: UK (138), Italy (74 -A, 57 -B), USAF (1763), USMC/USN
(680). <- US to acquire 513 F-35s over next 5 years (2007
schedule showed 461 so 52 accelerated buys expected.)
Australian (75-100) participation expected lot 5.
Italian (74 -A, 57 -B), Turkish (100-116) and likely Israel
(25 -A + 50 A/B?) participation expected lot 6.
Canada (65) Danish (48) and Norway (48) participation exp lot
8.
Singapore participation expected lot 8. Delivery ~2016 @ 8-12 a
year.
Production peak expected 2016 (2X per month, 2XX per year). In
comparison F-16 peak was 1987 (299 yr and 30 max
month).
Other interested countries:
Greece, Korea, Finland, Belgium, Spain.
Other potentials: Japan, India, Taiwan.
2004 flight int'l article:
"JSF team members pointed out...the F-35B especially well-suited to
the RSAF requirements."
http://www.flightglobal.com/articles/2004/02/25/179859/usaf-embraces-stovls-capabilities.html