Cost over-run: almost 20 times. Delay: 16 yrs, and
counting. Army says too heavy, too hot, Russian T-90s better; even
Minister admits tracks will be replaced by imported ones; DRDO says
we will build new one
New Delhi, November 13: The Arjun tank has no future. It still
cannot fire straight. The T-90, a far superior tank, can kill the
Arjun. We would not cross any border with these tanks.
Strong words, from Brigadier D K Babbar, the Armys pointsman for
the Main Battle Tank (MBT) Arjun project at the Mechanised Forces
directorate until he retired last year from the 94th Armoured
Brigade. Babbar, who spoke to The Indian Express, has reason to be
disillusioned. So has Army chief General J J Singh who was more
diplomatic last month: We will see where we can use it to get
optimum use.
Its not going to be easy.
Over 30 years after Project Arjun was sanctioned by Indira Gandhis
Cabinet to make a home-grown battle tank that would address the
armoured deficit identified during the 1971 war, the Army is now
faced with a troubling prospect: inducting a lumbering, misfiring,
vintage design tank like the Arjun, and that, too, in large
numbers.
This, after DRDO over-shot Arjuns project deadline by 16 years
from 1984 to 1995, finally closing the project only in 2000 and
the cost over-run is almost 20 times the original estimate. This is
the highest percentage over-run for any DRDO project.
With five pre-production tanks forced upon the Armys 43rd Armoured
Regiment in 2004 and 23 tanks to be handed over shortly, MBT Arjun
is about to be pushed into full-rate production outside Chennai,
with the Army bound by its commitment to buy 124 for two regiments,
all of which are to be delivered by 2008.
Still having 58 per cent of its content imported - including its
engine, the integrated gunners main sight and tracks the Arjun
tank was put through confirmatory trials in the Mahajan ranges in
July but the Army wasnt holding its breath.
Consider these: At a mammoth 58.5 tons, Arjun is a full weight
class over the Russian T-90 and nowhere near as agile.
In May, the Defence Ministry publicized the Army chiefs
inauguration of a product called Bogie Flat Arjun Tank (BFAT) built
by Bharat Earth Movers in Bangalore. What it didnt say: these were
specially built rail wagons wide enough and reinforced to carry the
massive 3.85-m-wide Arjun. For, the tank will crack the existing
freight wagons.
According to the Armys latest trials, the decade-old problem of
overheating persists. Two of the tanks main subsystems, the fire
control system (FCS) and integrated gunners main sight, which
includes a thermal imager and laser range-finder, are rendered
erratic and useless by the Arjuns abnormally high peak internal
temperature, which moves well beyond 55 degrees Celsius. This is in
testimony to the Parliamentary committee.
Following failed trials in summer 1997, which were criticized in
a 1998 CAG report for a series of malfunctions, transmission
failures and overheating, and an exodus of scientists from DRDO the
same year, the tanks production cost shot up steeply. Its unit
price in 1997 was Rs 10.8 crore. Its official unit price now: Rs
16.8 crore.
Former chief Gen Shankar Roy Choudhary had promised his service
quick inductions, only to be faced with yet another extension by
DRDO. In the same period, the Sino-Pak Al-Khalid tank was
productionised and had begun inductions. When contacted, Roy
Choudhary said: I was a strong proponent of the Arjun tank but its
performance was disappointing.
On October 12, Minister of State for Defence Production Rao
Inderjit Singh told The Indian Express that it was decided after
the recent trials that the production-series tanks will be
stripped of their indigenous tracks and will have imported ones. So
will the first few tanks that roll out of the Heavy Vehicles
Factory outside Chennai. In other words, after three decades of
research, Main Battle Tank Arjun cannot stand on its own
indigenous feet.
The project, according to testimony provided in January by the
Defence Ministry to the Parliamentary Standing Committee on
Defence, has produced virtually nothing. DRDO admitted to the same
committee in June that it would be able to develop an indigenous
engine, gunners main sight and tracks only if the Army places an
order beyond 124 tanks. However, the Army has no such plans, making
it uneconomical and non-feasible to reduce import content.
License production of the above items may be feasible with
enhanced order quantity for Arjun tanks and may result in reduction
in import contents, admits DRDO. It is, therefore, no surprise
that the Army will progressively begin inducting between 800-1000
T-90 Bhishma tanks, which will be built under license from Russia,
from 2008, making the letter M in Arjuns prefix not just
superfluous but bogus. Why?
It is important for the Army to maintain combat superiority over
its adversaries. There have been delays and slippages in the MBT
Arjun project, Army Headquarters said in written replies to The
Indian Express. Five months ago, the Parliamentary Standing
Committee on Defence said, The Committee also desires that
accountability for delay in production of the Arjun Tank may be
fixed. But the Arjun, which has cost the exchequer Rs 305.6 crore
so far (representing one of the largest ever cost-overruns in
percentage terms), has the influential DRDO high command
unfalteringly behind it. DRDO chief Manthiram Natarajan, chief
architect of the Arjun programme and a 2002 Padma Shri, has been
associated with the programme since its birth in 1974 and became
Programme Director in 1987. When contacted, he said, Defence
scientists are conscious that there have been time over-runs on
some of the projects. But even today, it is much more cost
efficient than tanks of same calibre being produced
elsewhere.
But DRDO is undeterred. With the Armys armour perspective plan
drawing out 60 regiments by 2020, DRDO told the Parliamentary panel
that its now developing what it calls Tank-X, a hybrid consisting
of an Arjun gun turret mounted on a T-72 chassis. Two tanks have
been prepared, and DRDO has said it will shortly offer them to the
Army for an evaluation. No guesses for why the Army isnt terribly
excited.
http://www.indianexpress.com/story/16589._.html
Stupid tank...full of nationalistic and Indians never start things
from basic steps and not within its capabilities! It's failure is
never in doubt! 58% of its component are imported, LOL!!!