Base on your information, can I say that the JEMP is expected to be
completed by Dec this year?
if they maintain this pace, we should be looking at a very
advanced stage of completion by year end, especially for the new
tracks. however they still have to join the new tracks to existing
tracks, and that cant go fast since they only have a few hours
every night.
but I think the station wont be that fast, even with the roof,
it is still essentially the skeleton. there are still mechanical
and electrical works (including another 54 sets of PSDs), as well
as various aesthetic works like tiling and painting.
dont forget there is testing to do as well. the targeted
completion date of project is 30th July 2011 by the way.