Some photos of the Basement KimChuan Depot..to be updated.
Total Trains
For Circle Line Operations: 40
Additional Orders: 7 (on option)
Current Trains
in KCD: 25
Last delivery
month: June 2008
Trains Not yet
delivered: 15
Trains
Handover by ALSTOM TO SMRT (after passed the test and certified by
LTA): 07
Cost for each train: SGD14 Million
General
Information
Do you know our Kim Chuan
Depot is the BIGGEST UNDERGROUND TRAIN DEPOT IN THE WORLD??. Yes!
in the world!. Hard to believe it but it is true!. Watch out for
the National Geography channel/Discovery Channel!